What is the last step a technician must perform when removing Lockout/Tagout (LOTO)?

Prepare for the SACA Pneumatic Troubleshooting (C-304) Test with interactive quizzes, featuring flashcards and multiple choice questions. Each question includes hints and detailed explanations to boost your confidence for the exam!

The last step a technician must perform when removing Lockout/Tagout (LOTO) is to test the machine. This step is critical to ensure that all systems are functioning correctly and safely before returning the machine to service. By testing the machine, the technician verifies that the lockout devices and safety precautions were effectively implemented and that there are no unexpected issues that might pose a risk to operators or maintenance personnel. It confirms that the machine operates as intended without any hazards before re-engaging normal operations.

While notifying others, reinstalling safety features, and documenting the process are all important aspects of the LOTO procedure, they occur before testing. Notifications and documentation ensure that everyone is aware of the machine's status and any relevant changes, while reinstalling safety features ensures all protective measures are in place before the machine is operational again. Testing the machine is the final and crucial step to confirm its safety and functionality.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy